Andhra Pradesh is planning large-scale deployment of Battery Energy Storage Systems (BESS) to improve power reliability and support integration of renewable energy. The programme targets a total capacity of 3,000 MWh in phases, with 1,000 MWh planned for completion by January 2027. Tenders are expected to be issued shortly, with participation from private developers.
The investment is estimated at around Rs 1.68 crore per MWh, with viability gap funding and central support expected to play a role. The state is also evaluating co-location of BESS with solar and wind projects to improve utilisation and system efficiency. Officials estimate that peak power procurement costs could decline from Rs 10 per unit to about Rs 4.85, resulting in annual savings of Rs 400–500 crore. Multiple substations and load centres have been identified, with priority given to areas with high renewable penetration.
The initiative is expected to reduce outages, improve supply quality, and strengthen the financial position of distribution companies by lowering power purchase costs. Declining battery prices and advances in grid technologies are supporting the viability of such projects.
The state government recently approved allocation of land for two ultra-mega solar parks in YSR Kadapa and Kurnool districts, each with a planned capacity of 1,000 MW, as part of efforts to expand grid-connected solar capacity.
The featured photograph is for representation only.
Author: PPD Team Date: October 9, 2025 PVV Infra Limited has won two solar power projects with a total investment of Rs 7.99 billion in Uttar Pradesh. Its subsidiary PVV EVTech has signed a 25-year power purchase agreement with the Uttar Pradesh New and Renewable Energy Development Agency for a 100 MW solar project across Baghpat and Moradabad districts. The project, developed with Nacof Oorja, will cost about Rs 3.84 billion and is expected to…
Author: PPD Team Date: October 30, 2024 Apar Industries recorded a 25% year-on-year increase in transformer oil volume in Q2FY25, driven by robust global demand. For the first half (H1) of FY25, transformer oil volume rose by 22.7%. Performance across other segments: ConductorsVolume growth remained flat in Q2FY25, primarily due to reduced exports amid increased competition from China and slow overseas demand. The export mix dropped to 18.7% from 48.3% in Q2FY24. Despite these challenges,…
Author: PPD Team Date: December 5, 2024 Mufin Green Finance has announced plans to finance Rs 5 billion worth of solar projects by 2026, marking its entry into the solar financing sector. The company recently closed its first solar financing deal worth Rs 32.5 million, supporting a rooftop solar installation at a manufacturing facility in Baroda, Gujarat, for a USD 3 billion company. Over the next two years, Mufin Green Finance aims to back 200,000…
Author: PPD Team Date: October 10, 2024 Saatvik Solar has secured a contract to supply 213 MW of solar photovoltaic (PV) modules to Larsen & Toubro (L&T) for its 245 MW battery energy storage system (BESS) project in Bihar. The project consists of 185 MW for a grid-connected solar power plant and 45.4 MW for a 4-hour battery storage system in Kajra district. As part of the agreement, Saatvik Solar will provide 545 Wp mono…
Author: PPD Team Date: July 11, 2025 Bharat Coking Coal Limited (BCCL), a subsidiary of Coal India Limited (CIL), has restarted coal production at its legacy PB Project in Jharkhand. This is the first operational project under the mine developer and operator (MDO) model in the CIL ecosystem. The PB Project has been awarded to Eagle Infra India Limited for a 25-year term. It is expected to produce 52 million tonnes of coal during its…
Author: PPD Team Date: December 17, 2024 Tamil Nadu Green Energy Corporation Limited (TNGECL) plans to develop 100 MW cumulative wind-solar hybrid power projects in the state. The projects are expected to be set up on a design, build, own, operate, and transfer (DBOOT) basis in Thoothukudi and Kanyakumari districts. TNGECL is preparing a detailed project report (DPR) for the initiative.