PFCCL transfers SPV for Kurnool-III transmission project
Author: PPD Team Date: March 31, 2025
Author: PPD Team Date: March 31, 2025
PFC Consulting Limited (PFCCL) has transferred Kurnool III PS RE Transmission Limited, a special purpose vehicle (SPV), to Power Grid Corporation of India Limited (PGCIL) for strengthening the transmission system at Kurnool-III PS. The transfer took place on March 27, 2025.
POWERGRID received the Letter of Intent (LoI) for the project on March 6, 2025. The project was awarded through Tariff-Based Competitive Bidding (TBCB) and will be executed on a build, own, operate, and transfer (BOOT) basis.
The project, which costs Rs 28.86 billion, will facilitate the integration and evacuation of over 4.5 GW of additional renewable energy capacity. It involves expanding transmission infrastructure, including the development of 400 kV line bays, augmentation of transformation capacity, and construction of a 765 kV double circuit (D/c) transmission line from Kurnool-III to Chilakaluripeta. PFCCL acted as the project’s Bid Process Coordinator (BPC).
Author: PPD Team Date: June 16, 2025 Power Grid Corporation of India Limited (PGCIL) has proposed the merger of 17 Inter-State Transmission System (ISTS) subsidiaries, set up under the Tariff Based Competitive Bidding (TBCB) route, into two existing TBCB subsidiaries. Under Part 1 of the plan, five subsidiaries will be amalgamated into Vataman Transmission Limited. These include: Bhadla III Transmission Limited Ramgarh II Transmission Limited Beawar Dausa Transmission Limited Bikaner III Neemrana Transmission Limited Sikar…
Author: PPD Team Date: April 2, 2026 The Ministry of New and Renewable Energy (MNRE) has approved guidelines for a pilot Contract for Difference (CfD) scheme covering 500 MW of renewable energy capacity. Solar Energy Corporation of India (SECI) has been designated as the nodal agency for implementation. The approval, dated March 30, 2026, follows proposals submitted by SECI in October 2025 and January 2026. Under the framework, generators will sell electricity directly on power…
Author: PPD Team Date: May 26, 2025 Juno Joule Green Energy Private Limited has signed a memorandum of understanding (MoU) with Germany’s Select Energy GmbH to co-develop a green hydrogen and ammonia export facility at Mulapeta port in Andhra Pradesh. The total investment for the project is estimated at $1.3 billion. The facility will be developed in three phases. By 2029, it aims to produce 180,000 tonnes of green hydrogen annually. This will be converted…
Author: PPD Team Date: August 11, 2025 Coal India Limited (CIL) has permitted the sale of unrequisitioned surplus (URS) electricity generated by thermal power plants using its linkage coal under long and medium-term fuel supply agreements (FSAs) in power exchanges and markets. Under earlier rules, such surplus generation could only be supplied under power purchase agreements (PPAs) and could not be sold in the market. The restriction has now been removed through a revision to…
Author: PPD Team Date: November 24, 2025 CERC will hold an online public hearing on December 3, 2025, to finalize the value of X used to calculate deviation percentages for wind and solar sellers under the Deviation Settlement Mechanism and Related Matters Regulations, 2024. The new framework will apply from April 1, 2026. The hearing follows a consultation launched on September 10, 2025. Stakeholders were first asked to submit comments by October 5, 2025. After…
Author: PPD Team Date: October 28, 2024 Adani Green Energy Limited (AGEL) reported a net profit of Rs 5.15 billion for the quarter ending September 2024, marking a 39% increase from Rs 3.71 billion in the same quarter last year. The company’s total income rose by 30.39% to Rs 33.76 billion during this period, up from Rs 25.89 billion recorded in the corresponding quarter of the previous year.